Contracting 101: Tracking Costs on a Firm-Fixed-Price Contract

Writer: Melissa Jones
Melissa Jones
7 days ago
11 min read

A firm-fixed-price (FFP) contract establishes the price the government will pay for the required work, subject to the terms of the contract. But that doesn't mean the contractor's costs are fixed, or that the contract will automatically be profitable.


Once a contract is awarded, someone needs to be responsible for understanding what it will cost to perform, monitoring what the company is actually spending, and predicting where the contract will finish financially. That responsibility falls under Program Control (PC).


For smaller contractors, PC may be handled by the owner, a finance employee, or someone who also performs contract administration. A dedicated Program Control department isn't necessary, but the function is. Without it, management can find itself making staffing, purchasing, and operational decisions without understanding their financial impact.


Program Control Should Begin at Contract Award

When a contract is awarded, one of the first Program Control activities should be developing a budget covering the anticipated life of the contract, including the base period and all option periods.

The proposal is the logical starting point. It contains the labor estimates, material costs, subcontractor pricing, indirect rates, and other assumptions used to develop the proposed price.

However, the awarded contract may not match the proposal exactly. Negotiated pricing, changes to the statement of work, revised staffing requirements, or different delivery schedules can affect the original assumptions. The budget needs to reflect the contract the company actually received.

PC should work with Contracts and the Program Manager (PM) to review the award, understand the performance requirements, and establish a financial baseline.


At a minimum, the budget should identify anticipated revenue, direct labor, subcontractor costs, materials, travel, other direct costs, applicable indirect expenses, and expected profit. These should be distributed across the periods when the work and costs are expected to occur.


For a multi-year contract, I recommend establishing the full-life budget at award while keeping the base period and each option separately identifiable. Unexercised options should remain distinguishable from authorized work.


Read the Contract Before Building the Budget

One of the biggest mistakes a contractor can make is assuming that an FFP contract's monthly revenue is simply the total contract price divided by the number of months in the period of performance.


That may be appropriate for certain contracts with evenly distributed services and monthly payment provisions, but it isn't universally correct.


The contract determines what the contractor must provide and the conditions under which payment is earned or may be invoiced.


For example:

Minimum staffing or FTE requirements. Some FFP service contracts specify staffing levels or productive-hour requirements and provide for invoice reductions when those requirements aren't met. PC needs to understand those provisions when forecasting revenue and staffing costs.


Required key personnel or positions. A contract may require particular positions to remain staffed, establish qualifications for personnel, or require government approval for replacements. Some contracts also tie payment adjustments to vacancies or staffing shortfalls. A vacant position may reduce labor costs while simultaneously creating performance risk or reducing the amount that can be billed, depending on the contract.


Milestone-based payments. Some contracts provide for payment upon completion or acceptance of specific milestones. PC must understand the timing of those events rather than assuming revenue or cash receipts will be evenly distributed.


Delivery-based contracts. A manufacturing contract may require completed units to be delivered and accepted before payment becomes due. Production costs can accumulate for months before the associated delivery payment occurs.


Quality and performance requirements. Contracts may provide for deductions, rework, or other remedies when performance doesn't meet contractual requirements. PC should account for identified financial exposure rather than assuming the full contract price will always be collected.


Uneven performance requirements. A contract may require significant effort during transition-in, initial equipment purchases, testing, or final delivery. Costs may be concentrated in certain months even when the overall price is fixed.


These examples are why Contracts, PC, and the PM need to work together during project setup. The financial model should reflect the actual award requirements, including CLIN structure, delivery schedules, acceptance provisions, and payment terms.


One additional distinction matters: billing and revenue recognition are not necessarily the same thing. A milestone payment may represent contract financing rather than earned accounting revenue. PC should coordinate with Accounting to ensure each is treated appropriately.


Budget vs. Forecast: What's the Difference?

The budget represents the financial plan established for the contract. It is the baseline against which performance is measured.


The forecast represents what the company currently expects to happen based on actual performance and updated assumptions.


Those two numbers will often become different over time.


Suppose a company receives a 12-month FFP contract for $500,000 and establishes an original cost budget of $400,000. The anticipated profit is $100,000, representing a 20% profit margin.

Six months into performance, actual costs total $190,000. Based on the original budget, that may appear favorable.


However, the PM now expects higher labor costs, additional coverage requirements, and increased subcontractor expenses. PC updates the forecast and determines that completing the remaining work will cost $240,000.


The resulting estimate at completion (EAC) is $430,000.

Financial Measure

Original Budget

Current Forecast

Contract revenue

$500,000

$500,000

Total costs

$400,000

$430,000

Profit

$100,000

$70,000

Profit margin

20%

14%

The contract hasn't exceeded its total cost budget yet, but the forecast is already identifying a $30,000 unfavorable variance.


This is why PC should preserve the original budget while regularly updating the forecast. If the original budget is continually overwritten, management loses the ability to measure how performance has changed.


Formal budget revisions may be appropriate when contract modifications or other approved changes alter the baseline. Those revisions should be documented rather than silently replacing the original plan.


How Far Ahead Should PC Forecast?

For service contracts with annual option periods, I recommend maintaining a detailed monthly forecast through the end of the current exercised option period.


That provides enough visibility to evaluate staffing decisions, anticipated raises, indirect-rate changes, subcontractor commitments, and remaining performance requirements.


PC should also maintain planning forecasts for unexercised options, particularly when future staffing, pricing, or purchasing decisions depend on them. Those projections should be identified separately because the government has not yet exercised those options.


For contracts without annual options, such as a manufacturing award with a defined production and delivery schedule, the detailed forecast should extend through completion of the contracted work.

The forecast should be updated at least monthly and whenever significant assumptions change.


Actual Costs Tell You What Happened. The Forecast Tells You What's Coming.

A useful Program Control report brings the original budget, actual costs, and remaining forecast together.


Actual costs should come from the company's accounting and timekeeping systems and reconcile to the appropriate financial records. PC needs enough detail to understand labor hours, employee or labor-category costs, subcontractor expenses, materials, and other costs associated with performance.


For labor-intensive contracts, the model should account for the company's applicable fringe, overhead, and G&A rates. If those rates change over time, the forecast should reflect the appropriate rates for each period rather than applying a single assumption across the entire contract.


A useful monthly report should show:

  • Original and current approved budgets

  • Actual costs incurred to date

  • Estimate to complete (ETC)

  • Estimate at completion (EAC)

  • Budget-to-actual and budget-to-EAC variances

  • Forecast revenue, profit or loss, and profit margin

  • Staffing, production, and performance assumptions

  • Identified financial risks and opportunities


Depending on the contract, PC may also track billing, collections, unbilled amounts, and cash-flow requirements separately.


A dashboard can make these results easier to interpret, but its value depends on the accuracy of the underlying data and assumptions.



Revenue Recognition: When Have You Actually Earned the Revenue?

Another important responsibility shared by Program Control and Accounting is understanding how the company recognizes revenue on an FFP contract.


Contractors sometimes treat revenue and billing as interchangeable, but they represent different things. Revenue reflects what the company has earned under its accounting policies and applicable accounting standards. Billing reflects what the contract allows the company to invoice.


There are several ways companies may recognize revenue on FFP contracts. The appropriate method depends on the nature of the work, the contract's performance obligations, and whether the requirements for recognizing revenue over time are met under ASC 606. A company's accounting policy should document the appropriate approach and apply it consistently.


Cost-to-cost recognition. This is a common method for long-term contracts where revenue is recognized over time. The company compares actual qualifying costs incurred to its estimated total costs at completion (EAC) to determine the percentage of work completed. That percentage is then applied to the applicable contract transaction price.


For example, if an FFP contract is worth $500,000, actual costs total $190,000, and the current EAC is $430,000, the contract is approximately 44.2% complete under a cost-to-cost calculation. That would result in approximately $220,930 in cumulative recognized revenue, assuming the costs appropriately measure progress and the entire $500,000 relates to the performance obligation being measured.


This is why an accurate EAC is so important. If PC updates the forecast because of increased labor costs, material prices, or production delays, that change can affect both projected profitability and the amount of revenue recognized. Changes in estimates may also require cumulative catch-up adjustments to revenue.



Labor-hour or other input-based recognition. Some contracts may use labor hours, machine hours, or other measurable inputs to determine progress instead of dollars spent. This can be appropriate when those inputs better represent the work being performed. For a labor-intensive service contract, productive hours may sometimes provide a more meaningful measurement than costs, particularly when employee pay rates vary significantly.


Time-elapsed or straight-line recognition. For certain recurring services, such as providing a consistent level of support throughout a contract period, recognizing revenue evenly over time may be appropriate when the customer receives the benefits evenly. However, this should not be assumed simply because the contract is FFP or invoices are issued monthly.


Milestone or output-based recognition. For contracts involving defined deliverables, production quantities, or measurable completion milestones, revenue may be recognized based on actual progress toward satisfying the performance obligation. A milestone must genuinely represent progress or transfer of value; a payment milestone alone doesn't necessarily establish that revenue has been earned.


Point-in-time recognition. Some product and manufacturing contracts require revenue recognition when control of the finished goods transfers to the customer, which may occur upon shipment, delivery, or acceptance depending on the contract terms. In those circumstances, accumulating production costs doesn't necessarily mean revenue can be recognized before delivery.


Billing-based recognition. This is one I approach cautiously. Recognizing revenue simply because an invoice was issued can distort financial performance, especially when invoices are evenly distributed but the work and associated costs are not.


A carefully developed billing schedule that accounts for predictable fluctuations in staffing, holidays, vacation periods, or production activity may improve financial planning. However, billing amounts can be used to measure recognized revenue only when the applicable accounting requirements are satisfied, including the right-to-invoice practical expedient where the amount billable directly corresponds to the value transferred to the customer.


For Program Control, the takeaway is that the forecast should provide Accounting with reliable estimates of costs, staffing, progress, and expected completion. PC doesn't independently establish the company's revenue recognition policy, but inaccurate forecasts can produce inaccurate financial reporting when revenue recognition depends on estimated progress.


And regardless of the method used, PC should be able to distinguish revenue earned from revenue billed when reporting contract performance to management.



Forecasting Labor Means More Than Multiplying Hours by Pay Rates

For service contracts, labor forecasting is often the most important part of Program Control.

PC should understand the anticipated staffing plan, expected productive hours, employee compensation, and the fully burdened cost of the labor required to perform the contract.


That forecast also needs to account for PTO, vacation, holidays, expected turnover, and replacement staffing.


Consider a contract requiring continuous coverage for five positions. If the forecast assumes five employees will each provide 40 productive hours every week, it may not account for vacation or holiday absences.


If coverage is contractually required, someone else may need to perform that work. That could mean overtime, part-time coverage, or additional employees.


The forecast needs to capture the cost of providing that coverage, while also recognizing any contract provisions that affect payment when staffing requirements aren't met.


Contractors should also be careful not to double-count paid leave. If PTO and holidays are included in the company's fringe allocation, those costs should be treated consistently with the accounting structure.


A good forecast reflects both the cost of employees and their actual availability to perform the work.

Your PM Should Be Able to Ask PC: Can I Afford This Hire?

This is where Program Control becomes particularly valuable.


Imagine a PM has an opening on an FFP contract and wants to know how much the company can afford to pay a replacement employee.


PC should be able to evaluate the proposed salary or hourly rate, remaining performance period, applicable indirect costs, available budget, and expected impact on profit.


For example, a PM may ask whether hiring someone at $95,000 instead of $85,000 will materially affect the contract's profitability.


PC should be able to model the difference, including applicable burden, expected start date, productive hours, and any anticipated coverage or recruiting costs.


The same applies when a PM wants to add another employee, approve overtime, replace a subcontractor, or change the staffing mix.


Those decisions should be evaluated before commitments are made, whenever possible.


And the answer shouldn't stop at whether the contract has enough money remaining. PC should be able to explain the impact on projected profit, margin, and financial risk, while the PM and Contracts determine whether the proposed staffing approach satisfies contract requirements.

What About Manufacturing and Product-Based Contracts?

The same Program Control principles apply to manufacturing, although the cost drivers and forecast assumptions may be different.


Instead of focusing primarily on labor coverage, PC may need to monitor production quantities, material requirements, procurement lead times, work in process, manufacturing labor, equipment usage, testing, and delivery schedules.


For example, a contractor producing 500 units under an FFP award may establish a budget based on expected material costs, manufacturing hours, scrap rates, quality inspections, and subcontracted components.


During performance, a supplier increases the cost of a critical component, or the production team discovers that each unit requires more assembly time than originally estimated.


Those changes affect the forecast even though the government has not changed the fixed price.


Manufacturing forecasts may need to account for:

  • Material price changes, shortages, and purchasing commitments

  • Production quantities, yields, scrap, and rework

  • Manufacturing labor hours and efficiency

  • Supplier and subcontractor delivery schedules

  • Tooling, equipment, and other production-related expenses

  • Inspection, testing, and acceptance requirements

  • Inventory and work-in-process costs

  • Delivery milestones and payment timing


PC should work closely with production management, procurement, and Accounting to understand those variables.


For manufacturing contracts, a useful forecast may be organized by unit, production lot, work order, or delivery milestone in addition to calendar month.


The objective is the same: determine what it will cost to finish the contracted work and whether the expected financial results are changing.


What Should the Minimum Program Control Process Look Like?

A small contractor doesn't necessarily need expensive software or a full-time Program Control analyst for every contract. The process can be scaled to the size, complexity, and risk of the work.


At a minimum, someone should be responsible for:

  1. Establishing the budget at award. Review the proposal and executed contract, identify revenue and cost assumptions, and establish a documented baseline covering the anticipated contract life.

  2. Maintaining a monthly forecast. Update remaining labor, materials, subcontractors, indirect costs, and other anticipated expenses through the relevant performance period.

  3. Reviewing actual costs. Obtain reliable data from Accounting, reconcile costs, and investigate significant differences from the budget and forecast.

  4. Evaluating profitability and risk. Calculate EAC, projected profit or loss, and margin while identifying staffing, production, billing, and performance risks.

  5. Supporting management decisions. Provide the PM and leadership with financial analysis before significant hiring, purchasing, or operational decisions.

  6. Reporting and documenting changes. Conduct regular financial reviews, explain material variances, and document assumptions and corrective actions.


This doesn't require a complicated reporting package. It requires consistent ownership, reliable information, and a willingness to use the numbers when making decisions.


The Value of Program Control on an FFP Contract

A contractor can meet its deliverables, submit invoices on time, and receive payment while its expected profit continues to decline.


Without a budget and a regularly updated forecast, that decline may go unnoticed until the contract is nearly complete.


Program Control gives management the information needed to understand the financial consequences of decisions before those decisions become expensive problems. It also provides a clearer picture of which contracts are performing well, which need attention, and what the company should consider when pricing future work.


For small businesses, the goal isn't to create an unnecessarily complicated process. It's to establish enough financial visibility to manage the work responsibly and protect the company's profitability.

At Ally Compliance Solutions, we help federal contractors establish practical Program Control processes, develop contract-specific budgets and forecasts, and build financial reporting tools around their accounting practices and contract requirements.


Whether you're managing a single FFP award or a growing portfolio of contracts, having someone responsible for the Program Control function is an important part of understanding how your business is actually performing.