You've received the award, everyone is excited, and it's time to get the project started. Somewhere along the way, someone schedules a kickoff meeting, invites a bunch of people, and puts together a presentation.


But what exactly are we trying to accomplish?


I've attended kickoff meetings where the team walked through nearly every page of the contract, and I've attended others where we covered the highlights and focused on getting everyone ready to perform. I've also seen companies skip the kickoff entirely because the effort was small or it was a follow-on contract.


There isn't necessarily one right way to do it. Every organization is different, and the size, complexity, and requirements of the contract should influence how the kickoff is conducted. What matters is that the right people understand their responsibilities, the requirements that affect them, and how the team will work together.


One important distinction before we get started: we're talking about the internal contractor kickoff, not a customer kickoff or formal post-award orientation. Depending on the contract, the government customer may require a separate kickoff meeting and dictate the agenda, presentation format, attendees, or specific information to be presented. Those meetings serve a different purpose and should be planned according to the customer's requirements.


What we're discussing here is how your company prepares its own team to perform the work. Here's an approach I like, but it's certainly not the only way to do it.


The Kickoff Actually Starts Before the Meeting

Ideally, the internal contract review should take place before the agreement is signed. The Contracts Administrator should send the draft agreement and applicable attachments to the appropriate stakeholders, identify the specific pages or sections each person needs to review, and request their concurrence or questions before execution.


And by stakeholders, I don't mean everyone who might occasionally hear about the project. I mean the people or departments responsible for performing, supporting, managing, or ensuring compliance with the contract requirements. Depending on the effort, that might include Program Management, Program Control, Accounting, Finance, HR, Recruiting, Security, IT, Quality, Purchasing, Subcontracts, and Operations.


Rather than sending a 150-page agreement with a generic request to review it, I prefer to direct each stakeholder to the specific sections, clauses, attachments, or page numbers that affect their responsibilities. For example, HR and Recruiting may need to review labor qualifications and staffing requirements, while Accounting and Program Control focus on funding, billing, reporting, and financial requirements. Security and IT may need to evaluate cybersecurity requirements, data handling, and system access.


Each stakeholder should respond with their concurrence or specific questions and concerns. That gives Contracts an opportunity to resolve issues, coordinate clarifications, and incorporate relevant feedback before the agreement is finalized, where possible.


It also creates a record that the responsible departments had an opportunity to review the requirements rather than discovering them after performance begins.


Of course, the timing isn't always ideal. Sometimes the agreement has already been executed or performance is about to begin. That doesn't eliminate the need for review; it just means the process needs to move quickly.


💡 Melissa's Super Helpful Tip

Sometimes you have the luxury of reviewing a contract well before performance begins. Other times, you're trying to complete the review within 24–48 hours of work starting. That's not much time, especially when you're asking people who already have full workloads to stop what they're doing and review contract requirements.

When you send the contract review email, make the urgency impossible to miss! Put the deadline in the subject line AND in the body of the email. I recommend using ALL CAPS and red font for the response deadline, and giving everyone a specific date and time rather than simply asking them to respond ASAP.

For example:

URGENT – CONTRACT REVIEW REQUIRED – RESPONSES DUE 11/12 BY 12:00 PM CST

Then repeat the deadline prominently in the body of the email and ask each stakeholder to respond with either their concurrence or specific questions and concerns.

And one more thing: no response does not mean concurrence. If someone misses the deadline, follow up directly and escalate unresolved issues when necessary. You don't want to find out at the kickoff that someone never reviewed their section because they thought they had until the end of the week. 😂


The Kickoff Is Not Necessarily a Contract Reading Session

Some organizations prefer to go through the agreement page by page, skipping sections that are primarily administrative or specific to Contracts. If that works for the company and the complexity of the agreement warrants it, there's nothing inherently wrong with that approach.


Personally, I prefer to do the detailed review beforehand and use the kickoff to cover the high points, introduce the team, discuss responsibilities, and highlight anything unusual or different from the organization's normal processes.


For example, if the company normally invoices monthly but this contract requires milestone billing, that deserves attention. If employees must meet specific qualifications, complete customer-required training, or follow unusual security procedures before starting work, those requirements should be highlighted.


The goal isn't to repeat every clause in the agreement. It's to make sure the people responsible for performance understand what matters to them and recognize where this contract differs from business as usual.


Don't Forget the People Who Won the Work

One group I believe should always be represented at the internal kickoff is Business Development and Pricing.


The kickoff represents the formal handoff from the people who pursued, proposed, priced, and negotiated the work to the team responsible for executing it. That transition is important, and it shouldn't consist of simply handing the Project Manager a copy of the award.


The BD and Pricing teams can explain how the work was proposed, what assumptions went into the estimate, what changed during negotiations, and whether there were any decisions the project team needs to understand.


For example, was a proposed position eliminated during negotiations, with the company agreeing to absorb the Project Manager's cost rather than charge it directly to the contract? Was pricing developed using 1,920 productive hours per FTE instead of 1,880? That difference can have a significant impact on labor budgets, staffing plans, and forecasts if the project team doesn't understand the basis of the estimate.


Another example is fee on other direct costs (ODCs). If the company agreed during negotiations to eliminate fee on ODCs, Accounting and Program Control need to know that when establishing billing, budgets, and forecasts.


These decisions may not be obvious to someone reviewing only the final contract value, but they can directly affect how the project is managed and whether financial performance is measured against the assumptions used to price the work.


It's also important to distinguish proposal pricing assumptions from actual contractual requirements. A particular FTE-hour assumption, for example, may be used to develop pricing and budgets without establishing a contractual requirement for each employee to work that number of hours.


HR and Recruiting Have a Seat at the Table, Too

I also like having someone from HR and Recruiting participate, particularly on labor-intensive contracts.


These departments may be responsible for finding employees who meet specific labor category qualifications, obtaining required documentation, coordinating onboarding, and ensuring that personnel are ready to begin work.


If the contract requires particular certifications, education, experience, background investigations, or customer approvals, the people responsible for hiring need to know about those requirements before recruiting begins.


And don't assume that the qualifications are the same as the company's standard job descriptions. Contract-specific labor qualifications can be very different, and substitutions involving education and experience need to be evaluated against the actual requirements.


It's much easier to address these issues before an offer is made than to discover afterward that the selected employee doesn't meet the contractual qualifications.


What About Subcontractors?

Depending on the size and complexity of the effort, subcontractors may also need to participate in the kickoff process.


For some projects, particularly those where subcontractors are heavily involved in performance or need to coordinate closely with the prime contractor's team, it may make sense to invite them to the internal kickoff for the portions relevant to their work.


For other efforts, I prefer holding a separate subcontractor kickoff. This allows the prime contractor to address internal matters, including financial information, staffing decisions, and company-specific processes, without unnecessarily sharing information that isn't relevant to the subcontractor.


Either approach is perfectly acceptable, and some projects may benefit from both.


What's important is that subcontractors understand their scope of work, deliverables, reporting requirements, communication procedures, and any applicable flowdown requirements before performance begins.


And remember, the subcontractor's obligations are established by the subcontract agreement. The kickoff is an opportunity to communicate and clarify those requirements, not to casually introduce new ones.


Cover the High Points, but Make Them Meaningful

The exact agenda will vary, but I generally want the kickoff to establish who is responsible for what and how the contract will be managed.


That includes introducing the key stakeholders and points of contact, reviewing the scope and period of performance, discussing significant deliverables and reporting requirements, and explaining the financial and operational expectations.


The team should understand the approved project structure and charge codes, applicable funding or spending limitations, billing requirements, staffing expectations, subcontractor responsibilities, and any unusual security, quality, or customer-specific requirements.


This is also where I would explain the communication and approval process. Who communicates with the Contracting Officer? Who handles contractual questions? How are potential scope changes identified and elevated? What happens when the customer asks for something that wasn't included in the original requirements?


And here's one point I would emphasize regardless of the size of the contract: employees should know to ask before making commitments to the customer.


A well-intentioned employee agreeing to perform additional work, change a deliverable, or adjust a schedule can create problems if the request hasn't been reviewed and approved through the appropriate channels. Not every customer representative has the authority to change the contract, and employees need to understand that distinction.


The purpose isn't to discourage communication with the customer. It's to make sure those conversations are handled appropriately and that the company understands the potential contractual, financial, and operational impact before agreeing to changes.


Don't Turn the Kickoff Into a Three-Hour Side Conversation

We've probably all attended a meeting where two people get into a detailed discussion that has absolutely nothing to do with the other fifteen people sitting in the room.


Sometimes those conversations are important. They just don't necessarily belong in the kickoff.

If an issue affects only one department or requires a lengthy technical or financial discussion, identify the responsible parties, document the action item, and schedule a separate follow-up. The kickoff should give everyone the information they need without consuming an entire afternoon discussing something that only concerns two people.


I also recommend documenting open questions, assigning owners, and establishing due dates. If the meeting identifies an issue that requires further investigation, someone needs to be responsible for making sure it gets resolved.


What About Small Contracts and Follow-On Awards?

Not every effort needs a formal hour-long presentation with representatives from every department. A small purchase order or a relatively straightforward follow-on agreement may not justify the same level of effort as a complex, multi-year contract.


But I wouldn't eliminate the communication entirely.


At a minimum, I would distribute a brief kickoff summary or set of slides identifying the key requirements, responsible personnel, and any changes from prior agreements, then give stakeholders an opportunity to ask questions.


And for follow-on contracts, please don't assume everything is the same just because the customer, work, or employees haven't changed.


Labor qualifications, wage determinations, reporting requirements, contract clauses, funding arrangements, cybersecurity obligations, and other terms can change between awards. Those differences need to be identified and communicated, even when the work itself looks familiar.

A shorter kickoff is perfectly reasonable. An uninformed project team is not.


Don't Let the Kickoff Presentation Disappear After the Meeting

I also recommend treating the kickoff presentation as a controlled project document rather than something that gets presented once and forgotten.


The final version should incorporate stakeholder feedback, corrections, and decisions from the meeting. Give it a revision date and version number, and store it with the project's contract management records where the appropriate team members can access it.


The presentation should also identify outstanding action items and responsible owners, or reference a separately maintained action log.


Six months from now, when a new Project Manager, Contracts Administrator, or Program Control employee joins the team, those materials can provide a useful starting point for understanding how the project was established, what requirements were highlighted, and why certain decisions were made.


Of course, the kickoff slides don't replace the actual contract. They're a practical reference to help the team understand and manage it.


Free Templates to Help You Get Started

If you're looking for a starting point, I've included two simple resources you can adapt to your own organization: a sample stakeholder contract review email and an internal project kickoff presentation.


The email provides an example of how to assign specific sections of the contract to the appropriate stakeholders, request concurrence, and establish a clear response deadline. The kickoff presentation offers a basic structure for communicating responsibilities, financial considerations, compliance requirements, and outstanding action items.


Neither is intended to be a mandatory checklist or a one-size-fits-all procedure. Some organizations will need additional detail, while others may be able to eliminate several sections entirely. Use what makes sense for your business, your contract, and the people responsible for performing the work.


One Last Thing: Make Sure Everyone Leaves Knowing What Happens Next

A successful kickoff isn't measured by the number of slides presented or how thoroughly someone reads the contract aloud. It's measured by whether the team understands its responsibilities and is prepared to perform.


Before wrapping up, confirm that everyone knows where to find the contract documents, who their primary points of contact are, what actions remain open, and how questions or potential changes should be handled.


And remember that the kickoff isn't the last time these departments should communicate. Contract modifications, new funding, option exercises, staffing changes, and evolving requirements may all create reasons to bring the team back together.


There are plenty of ways to conduct an effective kickoff, and the approach should fit the organization and the contract. The process I've described is simply one that I like because it encourages review before the meeting, focuses the discussion on what matters, and gets the right people involved early.


The goal isn't to get everyone through a presentation. It's to make sure everyone knows what they've agreed to deliver and how they're going to deliver it.